CWorking for

Accountable Government

 

Home
Up
TTC-69
Waller Co Toll Authority
Land Issues
Eminent Domain
Actions Taken
Voices
Calendar/Events
Links/Maps
Tools To Use
Archive

 

Hwy 290 Project

UPDATE 2008 : US 290 Project
Links: http://www.my290.com/index.htm & http://www.my290.com/Map.htm

The US 290 Project, which entails reconstruction of US 290 and Hempstead Tollway, covers a corridor of varying width that is approximately 38 miles long, extending from the interchange area of IH 10/IH 610/ US 290 northwest to FM 2920.

The overall vision for the US 290 Project includes:

  • Freeway capacity reconstruction and widening from IH 610 to FM 2920 to create:
    • Five general-purpose lanes in each direction from IH 610 to just west of Beltway 8, plus auxiliary lanes where appropriate
    • Four general-purpose lanes in each direction from just west of Beltway 8 to near the proposed SH 99/Grand Parkway, plus auxiliary lanes
    • Three general-purpose lanes in each direction from near the proposed SH 99/Grand Parkway to the west study limit, plus auxiliary lanes
    • Two- or three-lane frontage roads in each direction throughout the corridor

 

ALSO:

  • A four-lane, two-way managed lanes facility along Hempstead Tollway from IH 610 to the proposed SH 99/Grand Parkway
  • Two general-purpose lanes (possibly three) with curb and gutter in each direction to be reconstructed along Hempstead Tollway from IH 610 to Beltway 8
  • US 290 METRO HOV operations moved to the Hempstead Tollway managed toll lanes
  • Proposed high-capacity transit corridor located along Hempstead Tollway
  • Bicycle and pedestrian improvements

 

Phase I of US 290 construction, which includes the US 290/IH 610 interchange out to W. 34th Street, and Phase I of Hempstead Tollway construction, which goes from IH 610 to just west of Huffmeister, are both on track to begin in late 2010 or early 2011, with completion targeted for 2014.

 

When Phases II and III of US 290 construction will start is unclear at this point; work on those phases all depends on when funding becomes identified and there is resolution to current state and federal funding challenges as noted here. The sooner funding can be secured, the sooner construction on these phases can begin following completion of Phase I.

 

 Click to Enlarge Map

 


Some of you may be aware that there is presently underway a project on Hwy. 290 & Hempstead Hwy. with TxDOT. now beginning acquisition of land (& eventually using condemnation if necessary) to "expand" it from 610 to Grand Parkway - FM 2920)  I lifted the following from a site that describes the project: 

The Houston District of the Texas Department of Transportation (TxDOT), in cooperation with the Federal Highway Administration (FHWA), is considering improvements in the US 290 corridor from IH 610 to FM 2920, a distance of approximately 38 miles (including the Hempstead Highway corridor and the connections to the IH 610 West Loop). The Major Investment Study (MIS) & Environmental Impact Statement and Schematic Design (EIS) have been completed and the project is moving forward. The alternatives studied in the Environmental Impact Statement (EIS) will be variations of the multi-modal configurations suggested in the MIS: general-purpose lanes, managed lanes (possibly toll), and a reserve for advanced high-capacity transit (light rail/bus rapid transit).

Immediately below is the latest update (with interactive features) and below that is an earlier stage of the process.


Latest UPDATE:

US 290 Northwest Freeway Update Center


 

UPDATE April 12, 2006:  Roger Gonzales of TxDOT reports to the Association's Transportation Committee that the FEIS on US 290 may be approved by end of 2006 or early 2007.   Also, the tollroad element of the 290 Corridor can be underway in 2011 and the mainlanes of 290 underway in 2013.  Design packages should be out in September or October of 2006.
 

 

Click for Map and Letting Schedule

The Texas Department of Transportation (TxDOT) has undertaken a Major Investment Study (MIS) of the US 290 Corridor. This MIS studied the Northwest Freeway (US290 and Hempstead Highway) Corridor from Loop 610 in Houston to FM 2920 in Harris County.

The purpose of the study was to evaluate the future transportation needs of the Corridor and to evaluate alternatives in addressing transportation issues. The MIS evaluated various transportation alternatives to determine which alternatives were best to address congestion, traffic safety, and environmental issues along the Corridor.

This MIS was begun in 1999 and was completed in 2002.  Following the review of over 11 alternative treatments and three major public meetings with a total attendance of nearly 1000 residents and workers in the corridor, a recommended alternative was selected.

Preferred Alternative

The preferred alternative is to widen US 290 to 5 general purpose lanes in each direction between Loop 610 and the Grand Parkway.  In addition, it proposes 4 general purpose lanes from the Grand Parkway to FM 2920.

The preferred alternative also contains "advanced high-capacity transit" along Hempstead inside Beltway 8 and along US 290 outside BW 8.

In addition the alternative calls for a 4 lane, two-way, managed use facility along Hempstead.  This concept is similar to that being constructed in the Interstate 10 West corridor.  The difference is that the Hempstead facility will not be in the center of the freeway as is the I-10 project.   Click on these thumbnails for a schematic 

Current Developments

The project is entering preliminary design and the connection of US 290 at Loop 610 to Interstate 10 West is being redesigned to improve traffic flow in that highly congested corridor.

In addition, an evaluation is underway on the Hempstead managed use lanes as a tolled project, again similar to the managed use lanes on Interstate 10 West.

A major concern of the West Houston Association is the design of grade separations in the corridor.  We believe the major thoroughfares crossing both US 290 and Hempstead should be grade separated to improve mobility in the entire corridor.

Timing of the Project

If current studies prove out, the US 290 project should be constructed in phases with the Hempstead Managed Use Lanes built first as a toll revenue financed project. As with the I-10 managed use lanes, transit vehicles would be likely be allowed access so as to greatly improve transit capacity and trips in the corridor.  Second, the mainlanes of the freeway would be constructed after right-of-way is acquired.  Finally, the high-capacity transit facility would be constructed.


Early Project Description:

TxDOT-Houston District US 290 Major Investment Study

Maximization of existing right-of-way

Of the build alternatives, viable alternative 2 requires less right-of-way along US 290 inside Beltway 8; however, it requires the most right-of-way along

Hempstead Highway inside Beltway 8.  Of the build alternatives, viable alternative 3 requires the greatest amount of

right-of-way along US 290 inside Beltway 8; however, it requires the least right-of-way along Hempstead Highway inside Beltway 8.

Determining Locally Preferred Alternative

After thoroughly reviewing the previously described results, discussing

alternatives with the Steering and Advisory Committees, coordinating with

TxDOT, and gathering opinions and concerns expressed at public meetings, the

study team recommended a locally preferred alternative (generally viable

alternative 2 with some modifications) that includes the following improvements:

  • Five general-purpose lanes in each direction from IH 610 to just west of Beltway 8, plus auxiliary lanes where appropriate
  • Four general-purpose lanes in each direction from just west of Beltway 8 to near the future Grand Parkway / SH 99
  • Three general-purpose lanes in each direction from near the future Grand Parkway / SH 99 to the west study limit
  • Four-lane, two-way managed facility along Hempstead Highway from IH 610 to some location near the future Grand Parkway / SH 99
  • Two general-purpose lanes (possibly three) with curb and gutter in each direction will be reconstructed along Hempstead Highway
  • Advanced high capacity transit along Hempstead Highway from IH 610 to near the future Grand Parkway / SH 99
  • TSM / TDM / ITS improvements
  • Bicycle and pedestrian improvements
  • Two- or three-lane frontage roads in each direction (will be determined during schematic design)
Planning-level cost estimates indicate that the locally preferred alternative will cost $883 million in roadway construction (mobilization, contingency, and traffic control included), $35 million in right-of-way acquisition, and $873 million in AHCT construction The locally preferred alternative represented the most appropriate choice for the corridor when taking into account cost, constructibility, environmental impacts, and construction staging. The analysis of the alternatives led to the conclusion that all three of the major components studied in this MIS (general-purpose lanes, managed facility, and AHCT) are necessary elements of the locally preferred alternative. The locally preferred alternative provides congestion relief by having an acceptable LOS throughout the corridor; the new design presents a great opportunity to improve public safety in the corridor and it meshes well with METRO’s plans for transit in the corridor.

H-GAC’s Transportation Policy Council is the policy board ultimately responsible for adopting the locally preferred alternative. The implementation sequence for the locally preferred alternative is as follows:

  • Locally preferred alternative adoption by Transportation Policy Council
  • Harris County Toll Road Authority toll study for managed facility
  • METRO alternative analysis and environmental impact statement (AHCT details)
  • TxDOT schematic design and environmental impact statement
  • Plans, specifications, and estimates
  • Construction
 

 


Home | TTC-69 | Waller Co Toll Authority | Toll Roads | Land Issues | Eminent Domain | Actions Taken | Voices | Calendar/Events | Links/Maps | Tools To Use | Archive

Last updated: 06/02/08.